Washington, — The U.S. Army will miss its target of receiving the first MV-75 Cheyenne II tiltrotor for testing by the end of 2026 after exhausting its development funding earlier this year. The aircraft now has no confirmed delivery date.
The Office of the Assistant Secretary of the Army for Acquisition, Logistics and Technology (ASA(ALT)) confirmed the delay to Breaking Defense. The Army is working with Bell Textron, the prime contractor, to establish a revised schedule and assess programme risks.
Funding Shortfall Delays Development
The Army exhausted its available FY2026 development budget for the MV-75 by June. Bell continued development at its own financial risk but reduced spending. Formal communications between the company and the Army also stopped during the funding gap.
In July, the Army requested $350 million in budget transfers to support the construction and testing of eight prototype aircraft. Congress approved the request, and approximately $300 million was added to the contract on September 28 to cover costs already incurred by Bell and its suppliers.
Funding has resumed, but the Army has not announced a new delivery date.
First Aircraft Assembly Advances
Despite the delay, Bell has continued manufacturing. The company completed the first two wing structures in June and the engine nacelles in October.
On November 16, 2026, Bell completed the first full MV-75 fuselage at its Wichita facility in Kansas. It has since been transported to Amarillo, Texas, for assembly with the wings and nacelles. The completed aircraft will undergo structural testing and ground checks before flight testing.
FY2027 Budget and Production Plans
The Army requested more than $2 billion for the MV-75 in its FY2027 budget. However, delays in approving the full defence budget and the continuing resolution could affect the award of its low-rate initial production (LRIP) contract.
Textron executives warned that further delays could increase the company's financial impact by up to $150 million.
Replacing the UH-60 Black Hawk
Selected in December 2022 under the Future Long-Range Assault Aircraft (FLRAA) programme, the MV-75 is based on Bell's V-280 Valor demonstrator, which completed more than 214 flight hours between 2017 and 2021. The Army officially named it Cheyenne II in April 2026.
Designed for four crew members and up to 14 troops, the tiltrotor combines helicopter-style vertical takeoff and landing with fixed-wing aircraft speed and range.
The MV-75 is designed to cruise at 280 knots (approximately 320 mph), exceed 300 knots and achieve a combat range of 500–800 nautical miles. It is intended to provide roughly twice the speed and range of the UH-60 Black Hawk.
The Army plans military testing during 2027–2028, with operational deployment targeted around 2030, beginning with the 101st Airborne Division.